The planning application to build employment areas on parts of the former Carrington business park have now been submitted (planning ref: 108100/RES/22). The area within the red line is where the planning application relates to.
Indicative delivery dates: Start Q2 2023 | Complete Q2 2024
All the above ground demolition has been completed. The below ground demolition has been contracted to JF Hunt and will commence 27 August 2024 until November 2024, assuming no complications are found. in the area with the red border.
Site location (E4 and E6)
Building Heights
New trees and hedges
Proposed building designs
Site access
The entrance to the business park with be widened, a three way traffic light system installed and the bus stop indented off the main carriageway.
Tree Removal (The majority within the red boundary will be removed)
Demolition
Buildings highlighted in pink are to be demolished.