Site layout
Plant elevation plans
Visual impact on landscape
Approved 13 June 2022 with the following conditions, with associated applications for approval of conditions
Condition 1: Development must begin not later than three years from permission date
Condition 2: Construction completed as per submitted plans
Condition 3: Need full specification of all building material to be used | 108604/CND/22 Full discharge of conditions
Condition 4: Prior to occupation have completed a Remediation & Enabling work strategy
Condition 5: Remediation strategy. only if any more contamination is found | During construction
Condition 6: Piling not permitted without a report to demonstrate there is no risk to ground water | 108820/CND/22 Full discharge of conditions
Condition 7: Noise to be kept with levels defined in Noise Impact assessment | When operational
Condition 8: Compound fencing design, siting and colour | 108604/CND/22 Full discharge of conditions
Condition 9: CCTV and access controls, full details to be submitted prior to occupation | 109599/CND/22 Partial Full discharge of conditions
Condition 10: Soft Landscaping, full details to be submitted prior to occupation | 109599/CND/22 Partial Full discharge of conditions
Condition 11: Landscaping schedule to be submitted prior to occupation
Condition 12: Arboriculture Impact assessment to list all tree, hedgerows and scrubs to be retained
Condition 13: Car parking spaces can't be changed for any other use at a later date. | When operational
Condition 14: No clearance of trees and shrubs during nesting session
Condition 15: Redacted on report
Condition 16: External lighting scheme, full details to be submitted prior to above ground construction | 109599/CND/22 Partial Full discharge of conditions
Condition 17: Traffic management and servicing plan, full details to be submitted prior to development commencing | 108604/CND/22 Full discharge of conditions
Condition 18: Construction and Pre-construction environment plan (CEMP) to be approved before any demolition commences | 108604/CND/22 Full discharge of conditions
Condition 19: Facility not to exceed annual maximum of 3000 hours per engine | When operational
Condition 20: Development carried out as per drainage assessment
Condition 21: Drainage management and maintenance plan to be approved prior to above ground construction | 109057/CND/22 Full discharge of conditions
Condition 22: Site must has separate drainage system for foul and surface water